SUBMISSION OF REPORT DRAFT ( Week 13 )



Activity : Submitting the draft of FYP 1 report to the supervisor.



Objective : To ensure and help student finish FYP 1 report before the deadline.




Content/Procedure : 



1) Student need to finish up the report based on supervisor expectation.



2) Student need to submit the draft before 25 October 2019.






Result/Analysis :


1) All important task or subtopic are included inside the report. Student print the report and send it to supervisor as a draft.


2) Student manage to make Gantt chart and schematic diagram for the project as shown in Figures below. Gantt chart is important for the student time management and planning in order to complete the project. Meanwhile schematic diagram is important for the circuit configuration and connection of the project. 



FYP 1 Gantt Chart






Schematic Diagram of the project





Conclusion : As conclusion, student able to meet supervisor requirement and submit the report draft to supervisor before the deadline.